Wake Forest Reservoir dam improvements contract
Wake Forest
Summary
The Board hired WSP USA, with Falcon Engineering as subcontractor, for $699,625 to provide construction engineering, inspection, and dam safety services for the reservoir dam upgrades.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 15, 2026.
Impact analysis
$699,625 contract for construction engineering and inspection services.
Residents downstream of the reservoir and all users of the Town's water system.
Mentions & discussions (2)
Board of Commissioners - Sep 15, 2026
The Board hired WSP USA, with Falcon Engineering as subcontractor, for $699,625 to provide construction engineering, inspection, and dam safety services for the reservoir dam upgrades.
Board of Commissioners (Work) - Jun 23, 2026
The town is spending $7.63 million to upgrade the reservoir dam, using a $2.175 million congressional appropriation with a ticking spending deadline. FEMA's final approval was delayed four months by the federal shutdown, so the board locked in the contract now to be construction-ready the moment FEMA signs off.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Wake Forest
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.